The $1.5 billion effort to rid the Gowanus Canal of toxic sludge is so behind schedule and over budget due to government mismanagement that the canal may have to be re-dredged, according to the U.S. Environmental Protection Agency's watchdog.involving the removal of 600,000 cubic yards of cancer-causing coal tar, and the construction of two combined sewer overflow tanks that would limit toxic waste in the waterway. But the project is more than six years behind schedule.
The canal is one of the nation’s most seriously contaminated bodies of water, according to the EPA. Tanneries, oil refineries and numerous other industries in the area began using it as a dumping ground in the 19th century. It was placed on theof heavily contaminated sites in 2010, which initiated the cleanup process. Companies responsible for the contamination help foot the bill.
The report cited several reasons for the delay, including city and federal officials' failure to agree on multiple aspects of the project, including its design and schedule. The overflow tanks are now in the early stages of construction. “They're now dredging 600,000 cubic yards of this cancer-causing coal tar crud that's all along the bottom of the canal,” said Walter Hang, president of Toxics Targeting, which tracks contaminated areas. “The problem is they haven't abated the sources of pollution. And so the pollution continues to migrate into the canal.”
“EPA, the State of New York, and the City of New York simply ignored the endemic failure to comply with both the Superfund law and the Clean Water Act during a rushed redevelopment process that will ultimately increase the number of New Yorkers exposed to known contaminants,” the group wrote in an email.
The bottom of the canal contains an array of toxic chemicals including mercury, lead and compounds known as PCBs and PAHs, according to environmental experts.
United States Latest News, United States Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
Source: BreitbartNews - 🏆 610. / 51 Read more »
Source: NewYorker - 🏆 90. / 67 Read more »
Source: cbschicago - 🏆 546. / 51 Read more »
Source: soompi - 🏆 574. / 51 Read more »
Source: Gothamist - 🏆 456. / 53 Read more »
Source: soompi - 🏆 574. / 51 Read more »