“We expect the project infrastructure to be completed in December 2024 and operational by December 2026,' said the chairman of the State Works, Transportation, and Infrastructure Committee theSun theSundaily shuttle transport Singapore Malaysia

Johor Bahru-Singapore Rapid Transit System Link project is developing well, with work on various components such as depots, stations, land lines, and marine lines having achieved 32.42 percent completion.

“To ensure this project development runs smoothly, a task force was set up on Oct 21, 2020 to help facilitate any matter related to the state government such as land issues and so forth, with PLANMalaysia Johor as its secretariat.

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.
We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 25. in MY

Malaysia Latest News, Malaysia Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

JB-Singapore RTS Link project almost 33pc completed, says repJOHOR BARU: Work on the Johor Bahru-Singapore Rapid Transit System (RTS) Link project is progressing well and has now reached 32.42 per cent to include various components such as the depots, stations, land lines and marine lines.
Source: staronline - 🏆 4. / 75 Read more »

Johor Baru-Singapore RTS Link project almost 33pc completed, says excoJOHOR BARU, April 5 ― Work on the Johor Baru-Singapore Rapid Transit System (RTS) Link project is progressing well and has now reached 32.42 per cent to include various...
Source: malaymail - 🏆 1. / 86 Read more »

JB-Singapore RTS Link 32% completeJohor exco member says the project is running on schedule for completion by December 2026.
Source: fmtoday - 🏆 5. / 72 Read more »

Projek RTS Link Johor Bahru-Singapura capai kemajuan 32.42%Johor komited memastikan projek pengangkutan awam berimpak tinggi itu akan mula beroperasi pada 2026.
Source: fmtoday - 🏆 5. / 72 Read more »

Projek RTS Link JB-S'pura kini capai kemajuan 32.42% - paultan.orgBuat setakat ini, tahap kemajuan kerja projek Sistem Transit Rapid (RTS) Link Johor Bahru-Singapura telah mencapai 32.42%. Ini merangkumi pelbagai komponen seperti depoh, stesen, jajaran darat dan jajaran marin. Menurut Pengerusi Jawatankuasa Kerja Raya, Pengangkutan …
Source: paultan - 🏆 22. / 51 Read more »

T’gganu ECRL at 55% progressKUALA TERENGGANU: The construction progress of the East Coast Rail Link (ECRL) project in Terengganu has reached 55.21%, says Malaysia Railway Link Sdn Bhd.