Pan Borneo Highway: All remaining 16 work packages to start this year

  • 📰 DailyExpress_MY
  • ⏱ Reading Time:
  • 22 sec. here
  • 12 min. at publisher
  • 📊 Quality Score:
  • News: 47%
  • Publisher: 83%

Sabah News

News,Newspaper,Headlines

Kota Kinabalu: All 16 remaining work packages of the Pan Borneo Highway (LPB) project are expected to begin this year, said Deputy Chief Minister III Datuk Shahelmey Yahya.

Kota Kinabalu: All 16 remaining work packages of the Pan Borneo Highway project are expected to begin this year, said Deputy Chief Minister III Datuk Shahelmey Yahya.Shahelmey, who is also Works Minister, said currently 19 work packages are in the construction process, including four new packages for which contractor appointment letters had been issued.

Dear Daily Express reader,Ever since 1963, before the formation of Malaysia, The Daily Express has kept the public well-informed as well as helped shape Sabah & Labuan's development for 60 years.By subscribing you are supporting many of our award winning journalists - the first newspaper to win the Prime Minister's award for excellence in Journalism - who work tirelessly to bring you the facts and news that matter.

News Newspaper Headlines Malaysia Borneo Local National Business Sport Mobile

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.
We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 3. in MY

Malaysia Latest News, Malaysia Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

Main cause of delay for Pan Borneo Highway SabahKota Kinabalu: Changing the implementation method of the Sabah Pan Borneo Highway project in 2019 from Project Delivery Partner (PDP) to a conventional approach is the main cause for its delay, said Deputy Chief Minister III Datuk Shahelmey Yahya.
Source: DailyExpress_MY - 🏆 3. / 83 Read more »

Works minister: Land acquisition issues among factors for Pan Borneo Highway delay in SabahKUALA LUMPUR, March 21 — Land acquisition delays and changes in project implementation methods have led to slower progress in the construction of the Pan Borneo Highway (LPB) in...
Source: malaymail - 🏆 1. / 86 Read more »

Nanta: Land acquisition issues among factors for Pan Borneo Highway delay in SabahKUALA LUMPUR: Land acquisition delays and changes in project implementation methods have led to slower progress in the construction of the Pan Borneo ...
Source: theSundaily - 🏆 25. / 51 Read more »

Pan Borneo Highway project: 300 companies bid for tenderKUALA LUMPUR: A total of 300 companies have applied for the tender for Package 1B Phase One of the Pan Borneo Highway project involving 15 work packages, said Deputy Public Works Minister Datuk Seri Ahmad Maslan.
Source: DailyExpress_MY - 🏆 3. / 83 Read more »

Borneo Divers Mabul Resort receives four-star ratingSEMPORNA: Borneo Divers Mabul Resort (Borneo Divers) has been accorded the prestigious 4-star rating.
Source: DailyExpress_MY - 🏆 3. / 83 Read more »

Borneo Flyers, Borneo Eagles unggul pada hari pertamaSANDAKAN: Hari pertama Borneo Sevens 2024 berakhir dengan Borneo Flyers mengekalkan pendahuluan mereka dalam kategori Wanita.
Source: DailyExpress_MY - 🏆 3. / 83 Read more »