Lima LCS hanya siap 2029, kos bertambah RM2.098b

  • 📰 UMonline
  • ⏱ Reading Time:
  • 16 sec. here
  • 2 min. at publisher
  • 📊 Quality Score:
  • News: 10%
  • Publisher: 51%

Malaysia Headlines News

Malaysia Latest News,Malaysia Headlines

“Walaupun bilangan LCS dikurangkan kepada lima unit, namun, kos pembinaan LCS meningkat daripada RM9.128 bilion kepada RM11.22 bilion...

Tentera Laut Diraja Malaysia dijadual menerima lima kapal LCS serentak pada 2029 dan projek itu memerlukan kos tambahan RM2.098 bilion lagi.KUALA LUMPUR: Kerajaan dija­dual menerima kelima-lima kapal tempur pesisir pantai serentak pada 2029 tetapi memerlukan kos tambahan seba­nyak RM2.098 bilion lagi untuk menyiapkan projek tersebut. Tempoh masa pembinaan lima kapal tersebut turut dilanjutkan kepada 83 bulan lagi sebelum kapal-kapal diserah kepada Tentera Laut Diraja Malaysia .

Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.
We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 27. in MY

Malaysia Latest News, Malaysia Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

Lima LCS dijangka siap 2029, tambahan kos RM2.098 bilion'Isu utama berkaitan rekaan terperinci LCS belum diselesaikan. Kini berada pada kadar 96 peratus siap di peringkat kontraktor pembinaan...
Source: UMonline - 🏆 27. / 51 Read more »

Last LCS ready only in 2029, PAC report revealsAmos Yee is out on parole, barely halfway into his six-year jail term in the United States for grooming a teenage girl and possessing child pornography.
Source: staronline - 🏆 4. / 75 Read more »

PAC findings shows all five littoral combat ships will only be ready by 2029KUALA LUMPUR, Oct 9 — The Parliamentary Public Accounts Committee (PAC) report on the littoral combat ship (LCS) revealed that the fifth vessel is estimated to be completed by...
Source: malaymail - 🏆 1. / 86 Read more »

PAC findings shows all five littoral combat ships will only be ready by 2029Kuala Lumpur: The Parliamentary Public Accounts Committee (PAC) report on the littoral combat ship (LCS) revealed that the fifth vessel is estimated to be completed by 2029.
Source: DailyExpress_MY - 🏆 3. / 83 Read more »

Debt-stricken economies risk US$220bil in budget cuts, warns OxfamUnder current terms, debt and interest repayments total nearly US$500 million a day through 2029.
Source: fmtoday - 🏆 5. / 72 Read more »

Mindef should have got AGC’s approval before signing LCS supplementary contract, says PACThe defence ministry’s decision to bypass the Attorney-General’s Chambers in signing the contract could have legal implications for the government, says the committee.
Source: fmtoday - 🏆 5. / 72 Read more »