Zairil with Toh and Syerleena looking at The Light Interchange plan.
He also said the track leading to Karpal Singh Drive was closed indefinitely to facilitate widening of the expressway.“A better track for cycling and jogging leading to Karpal Singh Drive will be available along The Light City waterfront promenade when the development is completed in early 2025,” he told reporters at a press conference.
It is part of the state government’s Bicycle Lane Master Plan to create 120km of bicycle lanes encircling the island and another 80km on the mainland. “We will demolish the two pedestrian bridges located near the Caltex petrol station and next to the Coastal Runners statues in February and April respectively.Toh added that ownership of the Linear Park was shared by the Malaysian Highway Authority and the Drainage and Irrigation Department , and once the interchange was completed, maintenance might be from MBPP, subject to approval from LLM and DID.
Zairil said the bypass, which is one of the components under the Penang Transport Master Plan, was already 27% completed with bore-pile work and road widening taking place along Jalan Thean Teik in front of Farlim Market Complex.
Malaysia Latest News, Malaysia Headlines
Similar News:You can also read news stories similar to this one that we have collected from other news sources.
Source: staronline - 🏆 4. / 75 Read more »
Source: theSundaily - 🏆 25. / 51 Read more »
Source: malaymail - 🏆 1. / 86 Read more »
Source: staronline - 🏆 4. / 75 Read more »