The builder and operator of the Cavite-Laguna Expressway (Calax) has to spend more than the thoroughfare’s original project cost because of the delays in the delivery of right of way (ROW). Know more:

The builder and operator of the Cavite-Laguna Expressway has to spend more than the thoroughfare’s original project cost because of the delays in the delivery of right of way .

“We are now two and a half years delayed in construction because the right of way has been delayed for five years,” he said. “If there is opportunity to construct, if there is contiguous right of way, we continue to build.” This has caused the company to commit to open the said segment by the first quarter of 2023, a quarter delayed from the recent December 2022 commitment.

Source: News Formal (newsformal.com)

 

Thank you for your comment. Your comment will be published after being reviewed.
Please try again later.
We have summarized this news so that you can read it quickly. If you are interested in the news, you can read the full text here. Read more:

 /  🏆 19. in PH

Philippines Latest News, Philippines Headlines

Similar News:You can also read news stories similar to this one that we have collected from other news sources.

Right-of-way issues delays completion of CALAX subsection to Silang, CaviteThe completion of the subsection of the Cavite-Laguna Expressway (CALAX) linking the toll road to Silang, Cavite, has been delayed due to right-of-way issues, its developer and operator MPCALA Holdings Inc. (MHI) said.
Source: gmanews - 🏆 11. / 68 Read more »

Calax toll road is 15% costlier amid lockdowns, inflation spikeMetro Pacific Tollways Corp. has spent an additional 15 percent on building the 44.57-kilometer Cavite-Laguna Expressway due to delays in civil works and increase in construction material prices. | TyronePiad /PDI
Source: inquirerdotnet - 🏆 3. / 86 Read more »

Silang Interchange seen completed by first quarter“The target date of opening of the Silang [Aguinaldo] Interchange has been moved several times, with the latest target completion, being December of 2022 again uncertain,” MHI president Raul Ignacio said. READ:
Source: MlaStandard - 🏆 20. / 55 Read more »

Alagang Akay rolls out 200 wheelchairs for PWDs in Laguna - BusinessMirrorNagcarlan, Laguna, November 22, 2022. Independent non-profit and PWD-led Alagang AKAY donated wheelchairs for 200 Laguna-based Persons with Disabilities in ceremonies and festivities held here. The donation drive was held in cooperation with the Sol Aragones Foundation, former news reporter and three-term congressman Sol Aragones. 'One out of 7 people around the world or some
Source: BusinessMirror - 🏆 19. / 59 Read more »

MPTC won’t drop CTBEX despite overlap with San Miguel project - BusinessWorld OnlineTHE METRO Pacific Tollways group said it will not give up its original proponent status (OPS) for its unsolicited proposal to construct the 50.43-kilometer Cavite-Tagaytay-Batangas Expressway (CTBEX) despite San Miguel Holdings Corp.’s Cavite-Batangas Expressway (CBEX) overlapping with the project.
Source: bworldph - 🏆 9. / 68 Read more »

Cebu Chooks! snares 3×3 Quest 2.0 crownTallo had four deuces during his time on the floor, and these made a big difference as they claimed the last spot in the 16-team Hong Kong Masters. READ:
Source: MlaStandard - 🏆 20. / 55 Read more »